PROJECT REGISTER

1 Introduction

Table 8 below gives an account of physical projects being implemented in Second   Quarter of 2024. The Table provides information on the project description, development dimension of policy framework, the location of the project, the contractor/consultant, the contract sum, source of funding, date of award, date started, expected date of completion, expenditure to date, outstanding balance and the status of implementation as well as remarks. This information is presented under different funding sources being DACF-RFG, DACF, DACF/MP, and GOG.

 

 

Table 8: Project Progress Report on DACF, GOG, DACF-MP, DACF – RFG as at 30th  JUNE, 2024

PROJECT DESCRIPTION DEVELOPMENT DIMENSION OF POLICY FRAMEWORK LOCATION CONTRACTOR/ CONSULTANT CONTRACT SUM GH¢

 

SOURCE OF FUNDING DATE OF AWARD DATE STARTED EXPECTED DATE OF COMPLETION EXPENDITURE TO DATE OUTSTANDING BALANCE IMPLEMENTATION STATUS (%) REMARKS
Construction of 1 No. Maternity Wing at Asokore CHPS Compound

 

·        Project has been completed

Environment, Infrastructure and Human Settlement Asokore M/S Emebok B Enterprise 196, 000.00 DACF-RFG 31/10/2022 31/10/2022 31/04/2023 176, 400.00 19,600.00 100% Completed. Yet to be put to use
Construction of 1 No. 5 Unit Lockable Stores at Effiduase Market

Phase 1

·        Project has been completed

Environment, Infrastructure and Human Settlement Effiduase Market Asankare Company Limited 199,090.82

 

DACF-RFG 01/09/2022 04/11/2022 04/05/2023 189,136.28 9,954.542 100% Completed. Yet to be put to use
Construction of 1No. 2 Units KG Classroom Block at Asokore Salvation

 

The project is being painted.

Environment, Infrastructure and Human Settlement Asokore M/S Alfayi Company Ltd     184,486.96 DACF 01/08  /2021 23/02/2021 07/08/2021 131,477.60 53,009.36 95% On-going
Construction of 1No. 3 Seater W/C Toilet Facility at Effiduase R/C School.

·              Structure have been roofed. Spectik  tank and plumbing works  yet to be constructed

Environment, Infrastructure and Human Settlement Effiduase Emebok B. Enerprise 89, 256.30 DACF 20/02/2023 20/02/2023 05/05/2023 63,456.90 28,475.67 75% On-going
Construction of 1No. 3 Seater W/C Toilet Facility at Asokore Salvation School

·              Structure have been roofed. Spectik  tank and plumbing works  yet to be constructed

Environment, Infrastructure and Human Settlement Asokore Emebok B. Enerprise 89, 256.30 DACF 20/02/2023 20/02/2023 05/05/2023 63,456.90 25,799.40 75% On-going
Rehabilitation and conversion of existing community centre to a two storey Town Hall Complex at Asokore

 

 

The project’s superstructure is completed and has been roofed. Plumbing works is on -going.

Environment, Infrastructure and Human Settlement Asokore Kingdwosco Enterprise Ltd. 1,405,594.74 GoG 29/05/2020 29/05/2021 29/05/2021 1,059,517.16 346,077.58 95% On-going
Construction of 1No. 1 Storey Office Block Accommodation for Health Directorate Phase 1

 

Environment, Infrastructure and Human Settlement Jumapo Aduphill Ghana Ltd. 432, 529.32 DACF/MP 01/09/2022 19/10/2022 19/03/2023 402,845.93 29,683.39 100% Completed and in use
Construction of 1No. 1 Storey Office Block Accommodation for Health Directorate Phase 2 Environment, Infrastructure and Human Settlement Jumapo Kente Youth Association L.B. G 536, 590.00 DACF/MP 27/04/2023 01/02/2023 01/08/2023 509,190.50 27,399.50 100% Completed and in use